I have a project server farm 2016, I need to only copy projects with its project site (about 100 projects) from my old farm 2013 to the new farm

I don't want to do full migration, only Enterprise projects with sites need to copy it?

1 Answer 1

5

Unfortunately, there is no straightforward way to achieve your goal!


You have two options:

  1. Boring Manually Option

    • Manually Save all Projects Schedule and Upload it to the destination Project Server 2016 farm using Microsoft Project.
    • Then Import and export the Projects Subsites using PowerShell.
  2. Migration Option

Note: this option will lead to removing all settings that have been implemented in Project Server 2016 like Permission Settings, New Lists, sites, current projects...etc

Check also Install and configure Project Server 2016.